ESV’s technical report into the failure of a 66kV transmission line at the Salt Creek Wind Farm near Terang has been completed. ESV conducted independent testing to verify conclusions from the transmission line’s owner and operator, AusNet Services, that a firearm had been used to fire bullets at the insulator.